Estimate is one of important documents from which the repair, construction or reconstruction of any object begins. Drawing up an estimate for apartment renovation is a mandatory procedure that is primarily necessary for the Customer. This fundamental document must be prepared as an annex to the contract.

ORDER AN APARTMENT RENOVATION

Calculation of estimates for apartment renovations is carried out by a specialist - estimator. To begin with, our specialist goes to the repair site, inspects the premises, takes measurements of the premises, gets acquainted with the condition of the floors, ceilings, walls, windows and doors, finds out the individual wishes of the Customer and receives technical specifications.

Based on all the information received and measurements of the premises, project documentation and an estimate is drawn up for major renovation apartments. You can, perhaps, do without an estimate only if you are carrying out small redecorating or partial renovation of the interior. But still, an estimate is always needed; a description of the types of work included in the estimate undoubtedly gives a number of advantages when working on construction site during repairs. Thanks to the preliminary estimate, the Customer receives detailed information on the list of types of work and materials required for repairs, and also sees an accurate calculation of the cost of these finishing works and materials.

A typical commercial estimate does not look like an Excel table, which must indicate the types of work, units of measurement and cost. Our company uses the services of experienced estimators; we also constantly monitor prices for building materials, which allows us to significantly save money.

You, as a customer, have the opportunity to control the progress of work and expense items. When choosing a contractor to carry out work, it is the analysis of the estimate that gives a complete picture of the cost of the work and allows you to evaluate the professionalism of the contractor.

We can immediately tell you that prices for comprehensive repairs are significantly lower than for individual species works Each order is individual! The cost of services depends on the types of work and their volume. Moreover, the larger the volume, the lower the price for repairs. Finishing work.

Sample estimate for finishing work

No./pos.

Name of works

unit.

Quantity

Price, rub

Amount, rub

Dismantling work, garbage removal

Cleaning

Cleaning walls down to concrete (from wallpaper, putty)

Cleaning the ceiling down to the concrete (high-pressure paint, putty

Cleaning the floor down to concrete (from the old coating)

Other dismantling

Dismantling the baseboard

Taking out the trash

Removal of construction waste

Electrical work

Wiring of electrical, telephone and television networks in walls and ceilings

Installation of sockets, switches, spotlights, automatic machines

Plastering walls and leveling the floor (screed)

Primer for concrete walls and ceilings

Leveling ceilings (improved plaster)

Wall leveling (improved plaster)

Painting works

Wall putty

Ceiling putty

Pasting walls vinyl wallpaper

Ceiling painting water-based paint in 3 layers

Cleaning and painting pipes with heat-resistant paint

Carpentry work

Laying the ceiling cornice, filling and painting (foam or polyurethane, width up to 3 cm)

Tile work

Masonry ceramic tiles on the floor

Cleaning

Repeated cleaning throughout the renovation and at the end of the renovation

Total for finishing work:

CUSTOMER

CONTRACTOR

__________

__________

Sample estimate for rough material

No./pos.

Name

unit.

Price according to estimate, rub

Estimated amount, rub

Materials according to the main estimate

Plaster mixture "Rotband"

Betonokontakt mixture, 5kg

Insulating tape

Mounting boxes

Junction boxes

Alabaster G-5 ( gray) 20kg each

Copper wire in double insulation PUNP 3x1.5

Copper wire in double insulation PUNP 3x2.5

Putty "Vitonit-LR" (Fin.)

Ready-made finishing putty SHEETROCK 5.6kg (3.5l) ready-made putty

bucket 3.5l

Primer deep penetration, canister 10l

Latex-based water-based paint Fincolor Euro-7, white matte 9l

Tile adhesive Fliesenkleber KNAUF, 25kg

Polyethylene rolls 3 m wide

Dowels, screws, self-tapping screws, nails, bolts and other fasteners

Consumables and auxiliary materials, one-time tool

Total for construction and finishing materials

Fare, loading work, overhead costs, Unexpected expenses, tool depreciation, budgeting, etc. from the cost of materials

Total from transport costs and other expenses

Dismantling, construction and finishing works, waste removal

TOTAL estimated costs

59749

CUSTOMER

CONTRACTOR

__________

__________


To roughly calculate the cost of renovation of premises, use our online calculator. On our online repair cost calculator, you can calculate approximate cost repair work with rough materials. You just need to choose the type of repair (cosmetic repairs, major repairs, European-quality renovation), select the name of the room in which you are going to make repairs, then enter the area of ​​​​the room in square meters by gender, and the rest Online calculator it will calculate everything itself and display it in the column Total approximate estimated cost your renovation of premises.

Premises renovation cost calculator - online

If you do not want to manually calculate the floor area or you did not understand something when describing the calculations, then you can use our calculator and calculate floor or ceiling area automatically.

For calculation it is necessary measure in meters length, width of the room and enter the data in order by filling out the form and you will automatically receive a calculation floor or ceiling area in square meters.

Calculator for calculating floor and ceiling area

N let's keep you busy mathematical calculations. You just need to measure the basic parameters, and the wallpaper calculator itself will roughly calculate required quantity wallpaper for your room. Those who want more accurate calculations and measurements can read the article above How to calculate how much wallpaper you need.

Sample of a ready-made estimate for repair and finishing work in an apartment with total area 64 m2 new building at the address: Residential complex "Finsky-Potapovo microdistrict 3A".

Estimate No. 4 for repair and finishing work

Estimate for the purchase of rough materials

Name of works Unit change Qty

Price

in rub.

Price

in rub.

Dismantling works
1 Joining ceiling seams(Rustov) p.m. 8 150 1200
2 Dismantling sockets, switches, lamps PC. 12 75 900
3 Dismantling the electrical panel assembly PC. 1 650 650
Total: 2 750
Construction works
1 Laying partitions from tongue-and-groove blocks or foam concrete up to 100 mm thick sq.m 5,8 420 2436
2 Metal jumper device p.m. 2 280 560
3 Construction of a bathtub screen made of blocks PC. 1 1100 1100
4 Vapor thermal insulation device ("penofol", "penoplex") balcony - floor, ceiling, walls sq.m 27 360 9720
5 Coating thermal insulation device "Akterm" sq.m 0 180 0
6 Waterproofing of joints adjacent to the street sq.m 6 185 1110
Total: 14 926
Painting and plastering works
1 Plastering walls (along beacons) up to 20 mm sq.m 25 385 9625
2 Leveling walls (usually) up to 10 mm - rooms, kitchen, corridor, storage room sq.m 154,5 200 30900
3 Leveling ceilings (usually) up to 10 mm kitchen, corridor, pantry, balcony sq.m 28 250 7000
4 Sealing ceiling seams (rusts) p.m. 8 150 1200
5 Surface primer (2 layers) ceiling, walls sq.m 0 60 0
6 Final sanding surfaces - ceiling, walls sq.m 0 45 0
7 Puttying ceilings for painting (set of works) kitchen, corridor, pantry, balcony sq.m 28 350 9800
8 Painting ceilings with high-quality paint in 2 times sq.m 28 180 5040
9 Puttying walls for painting (set of works) sq.m 154,5 280 44805
10 Painting walls with high-quality paint in 2 times sq.m 154,5 140 21630
11 Plastering window slopes up to 300 mm p.m. 15 260 3900
12 Puttying slopes for painting (set of works) p.m. 15 280 4200
13 Painting slopes with high-quality paint in 2 times p.m. 15 180 2700
14 Installation of arched painting corners with sealing of seams and joints p.m. 22 65 1430
15 Painting of pipes with a diameter of up to 50 mm p.m. 26 120 3120
Total: 145 350
Carpentry work
1 Installation door block (ready set) PC. 5 3000 15000
2 Device slatted ceilings(up to 10 sq.m) sq.m 4,4 880 3872
3 Installation plastic window sills up to 300 mm p.m. 4,5 750 3375
Total: 22 247
Tile work
1 Wall tiling (size 250-250 mm) bath, toilet sq.m 25 850 21250
2 Hatch installation PC. 1 418 418
3 Construction of a tile hatch (with installation of a mechanism) PC 1 1100 1100
4 Laying tiles on the floor (size 300-300 mm) bath, toilet, balcony sq.m 10 700 7000
5 Drilling holes in tiles PC. 12 160 1920
6 Grouting ceramic tiles (monocolor) sq.m 35 100 3500
7 Trim sills made of tiles p.m. 1 1000 1000
Total: 36 188
Floor installation
1 Waterproofing floors in bathrooms sq.m 4,4 185 814
2 Leveling screed device up to 3 mm sq.m 54,4 150 8160
3 Laying laminate (with backing) sq.m 54,4 280 15232
4 Threshold installation p.m. 3 150 450
5 Installation of skirting boards p.m. 65 130 8450
Total: 33 106
Ventilation work
1 Box in ventilation duct PC. 1 319 319
2 Installation ventilation duct(up to 2 m) PC 2 1650 3300
3 Fan installation (with connection) PC. 2 308 616
Total: 4 235
Heating
1 Remaking the heating radiator supply unit PC. 3 4500 13500
2 Installing a heating radiator PC. 3 1500 4500
3 Removing/installing the radiator for finishing work (without dismantling the bracket to the finished location) PC. 3 500 1500
Total: 19 500
Plumbing work
1 Temporary water supply device set 1 1650 1650
2 Installation of a plumbing fine p.m. 6 600 3600
3 Sealing a plumbing hole p.m. 6 120 720
4 Filter installation fine cleaning with pressure regulator PC. 2 1400 2800
5 Collector installation (work package) PC. 2 2000 4000
6 Laying of HGV pipes (m/layer, p/propylene, p/ethylene) p.m. 26 270 7020
7 Pad sewer pipes(PVC) p.m. 5 330 1650
8 Thermal insulation of pipes p.m. 26 50 1300
9 Installation storage water heater(boiler) PC. 1 3300 3300
10 Installation of the Compact toilet PC. 1 2805 2805
11 Installation of "moidodyr" PC. 1 3000 3000
12 Mixer installation PC. 1 850 850
13 Installation hygienic shower PC. 1 850 850
14 Installation of a heated towel rail PC. 1 3300 3300
15 Bath installation PC. 1 3700 3700
16 Installing a Bathtub Faucet on a Rod PC. 1 1250 1250
Total: 41 795
Electric installation work
1 Installation of fines up to 30x30 mm p.m. 16 275 4400
2 Sealing the fine p.m. 16 35 560
3 Cabling p.m. 255 50 12750
4 Installation of a socket box (with a socket device) PC. 33 300 9900
5 Installation of overhead electrical distribution board PC. 2 650 1300
6 Installation of circuit breakers, differential circuit breakers, RCDs PC. 12 250 3000
7 Installation of socket, switch PC. 30 130 3900
8 Installation of TV, Telephone, Internet sockets PC. 3 180 540
9 Installation of TV, Telephone, Internet splitter PC. 1 280 280
10 Installation of a built-in (spot) lamp PC. 6 200 1200
11 Installation of electric heated floors sq.m 2 750 1500
12 Installation of underfloor heating relay PC. 1 350 350
13 Marking electrical installation locations (without design) PC. 33 35 1155
Total: 40 835
Total for work: 360 932
Total according to estimate No. 4: 360 932

Table No. 1 of consumption rough material.

Table No. 1 according to the consumption of construction and finishing rough materials in an apartment with a total area of ​​64 m2, a new building at the address: residential complex "Finsky-Potapovo microdistrict 3A".

Examples of a table for recording the consumption of rough material

Name

material

pcs/m2

bags

price

general

price

1 “Rodband” mixture with a layer thickness of no more than 2 cm 87 370 32190
2 Sand concrete M300 with a screed layer thickness of no more than 5 cm 145 160 23200
3 Lighthouse plaster 0.6 45 40 1800
4 Lighthouse plaster 1.0 12 45 540
5 Betokontakt "EURO" 3 1350 4050
6 Primer "Prospectors" 5 450 2250
7 Foam block No. 5 in pieces 6 45 270
8 Foam block No. 7 in pieces 84 55 4620
9 Moisture-resistant plasterboard 12 2 370 740
10 Gypsum putty "Fugenfühler" 1 750 750
11 Assembly adhesive for Perlfix blocks 3 320 960
12 Tile adhesive "Flizen" 6 350 2100
13 Self-leveling floor "Prospectors" 8 320 2560
14 Putty "Vetonit" LR+ 9 750 6750
15 Spider web "Oscar" 50m2 1 1150 1150
16 Profile 27/28 "Knauf" 6 100 600
17 Profile 60/27 "Knauf" 4 130 520
18 Finishing putty"Pro Form" 1 1350 1350
19 Pendant "Knauf" 40 20 800
20 Film -150 density 60 50 3000
21 Planed timber 50/50 3 200 600
22 Planed board 150/20 3 300 900
23 Garbage bags 120 10 1200
24 Glue for cobwebs "Oscar" 1 1350 1350
25 Coating waterproofing "Ceresit 65" 6 750 4500
26 Rule 2.5 1 500 500
27 Rule 2.0 1 400 400
28 Rule 1.5 1 300 300
29 Dowel nail 60/40 2 250 500
30 Facade mesh 160 density 1 1250 1250
31 Putty "Uniflot-Knauf" 1 1100 1100
32 Bucket 12 liters 2 120 240
33 Bucket 20 liters 2 180 360
34 Tank 60 liters 1 350 350
35 Paper masking tape 5 70 350
36 Packing tape 2 70 140
37 Self-tapping screws 0.35 universal 2 130 260
38 Self-tapping screws 0.65 for wood 1 130 130
39 Self-tapping screws 0.75 for wood 1 130 130
40 Self-tapping screws 0.25 universal 2 130 260
41 Painting corner galvanized 18 35 630
42 Alabaster in bags 1 280 280
43 Silicone in tube 1 140 140
44 Glue in a tube "FixAll" 1 420 420
45 Crosses 1.5 for tile joints 4 100 400
46 Wedges for tile joints 2 100 200
47 Cable NUM 3/1.5 "Sevkabel" 100 35 3500
48 Cable NUM 3/2.5 "Sevkabel" 150 47 7050
49 Cable NUM 3/4 "Sevkabel" 36 82 2952
50 Cable NUM 3/6 "Sevkabel" 5 95 475
51 Corrugation 16 100 3 300
52 Corrugation 20 200 4 800
53 Internet cable "FTP" 10 22 220
54 TV cable "SAT 703" 40 25 1000
55 Telephone cable "KSPV" 10 12 120
56 Crab TV 1/3 1 250 250
57 Insulating tape 1 40 40
58 Punched tape 1 180 180
59 Lamp 150v 5 40 200
60 Socket boxes for concrete 50 10 500
61 Automatic 10 amp. "ABB" 2 150 300
62 Automatic 16 amp. "ABB" 3 150 450
63 Automatic 25 amp. "ABB" 5 150 750
64 RCD "ABB" 1 1250 1250
65 DIF automatic 25 amp. 1 1350 1350
66 Armature 12 3 220 660
67
68 Lifting material "in tons" 8 1500 12000
69 Delivery of materials "gazelle" 4 1500 6000
70 Total: 147 787

An estimate for repairs is a cost calculation construction work and materials. Estimates are prepared both for construction and finishing work of premises (buildings) and for individual types of work. According to the estimate documentation, funds are allocated for construction and renovation work. We will tell you how to create an estimate for repairs in our consultation.

Repair estimate

The estimate is a mandatory appendix to the contract for construction and finishing work. An estimate for repair work is drawn up so that the parties to the contract have a clear idea of ​​the amount of costs, as well as what kind of work needs to be done, in what time frame and by which specialized organizations. In addition, the presence of an estimate helps the customer control the volume and quality of work performed, technological processes, as well as rising prices estimated cost.

As a rule, an estimate for repairs is drawn up design organization or a construction company independently. The estimate is drawn up based on spending standards building materials, taking into account the market cost of materials and work.

The objects of construction and repair can be buildings, structures, private houses, apartments or separate rooms. Next, we will tell you how to make an estimate for the renovation of a room, a sample of which will be given below.

Estimate for room renovation

The estimate for the renovation of the premises is drawn up in free form, according to a developed and approved template, each organization independently (Information of the Ministry of Finance of Russia N PZ-10/2012).

The estimate for repairs must contain the mandatory details provided for in paragraph 2 of Art. 9 of the Law of December 6, 2011 N 402-FZ:

  • name and date of preparation of the document;
  • names of the parties who entered into an agreement for repair work;
  • position, full name and signature of representatives of the parties to the contract authorized to approve the estimate;
  • name of materials and work, unit of measurement, quantitative expression, price per unit and total cost.

For convenience, the estimate can be divided into stages (for example, depending on the type of work - dismantling, network wiring, finishing).

We will send the material to you by e-mail

Long-awaited renovation in the apartment! In order for you not to hate it in a couple of years, you need to prepare for it. An example of an estimate for the renovation of a room will help with this, because such data will show how much and in what volumes you need to invest to get the home of your dreams. This is not just a list of purchases, but a whole document that can be entrusted to specialists, but be prepared for inflated costs. You can just as successfully compose it yourself, it’s just important to know how.

The estimate includes all expenses, calculates any unforeseen costs, including the services of specialists different directions. In order to make an estimate, you need:

  • Take measurements of the room. This includes the height and length of all walls, the length of wiring, cables, water supply and thermal communications, if any are included in the repair. After receiving information on dimensions, you can, which will become the basis for calculating the necessary roughing and finishing materials. It is important to have data on the area of ​​walls, floors and ceilings.
  • Based on the data obtained, it is necessary to calculate rough materials - make a reserve of at least 5-10% in this case.
  • Next comes the selection and calculation of the necessary decorative materials.
  • Now comes the most interesting and exciting part: price monitoring. You need to know how much draft and Decoration Materials, the cost of services of a designer and a team of repairmen, plumbers, electricians and other specialists who may be involved in the repair process. It is best to draw out a table and indicate several options for each item - this will allow you to avoid making a mistake with your choice.


All received data must be recorded and then compiled into one table: this way you will have a work plan + the cost of materials and the cost of paying specialists. It is also necessary to indicate the timing of the work, and if the injection of funds is partial, then their dates of such receipts.

Nuances

The estimate is not only Technical information, it includes an element of creativity. Technical aspect- this is at least minimal knowledge of the processes that will occur during the repair, an understanding of the building materials market, what is needed for what.


Creativity– this is the competent distribution of all cost items in accordance with the needs at a particular stage of work. It is important to take a balanced approach to choosing a team if you trust this to specialists. Don't flatter yourself low prices– it’s likely that the quality there will be the same. It’s better to make an estimate yourself; minimal data and numerous templates will help you with this. Why is it better to do it yourself? Everything is very simple: when ordering an estimate from a construction company, you will probably end up with a 20 or even 30% larger amount than it actually is. If you doubt the truth of the data, then you can very well use the services of another “specialists” - these are auditors. As practice shows, the cost of the estimate will decrease by no less than 10%.

Examples

The photo below is an example of an estimate for a kitchen renovation. All types of work are arranged into categories for convenience. These types of estimates for room renovations will help you navigate and quickly figure out how much money will be spent on individual parts.

There are separate subsections dismantling work. When carrying out a major overhaul, there will be a need to dismantle not only the old finishing, but also pipes, including sewer pipes. And given that the apartment has plumbing, this work will also affect the bathroom. It is rational to carry out renovations in the bathroom/toilet and kitchen together: this way you can save money. Next comes the treatment of the walls, floor and ceiling. Here you can see that roughing and finishing work are included in one table; we would recommend separating them.

Also important stage When drawing up estimates, the installation of plumbing fixtures is not included. If it is better for specialists to finish welding the riser, since you have decided to use their labor, then it is quite possible to connect the mixer yourself; no serious skills or complex tools are needed for this.


As you can see, there are columns with units of measurement, areas and lengths of all work items. For ease of calculation, the price per unit of work and then the total cost are indicated. The estimate will extract more funds if you instruct construction company purchase of materials. But be careful here: replacement is often practiced quality materials and components for low-grade ones. Therefore, it is important to control every stage of the work.

The following is presented approximate estimate for the renovation of the entire apartment, there is a slightly different drawing up scheme, but the meaning is the same. That is, unit prices and the total cost of work are indicated. As we can see, here the customer will most likely entrust the company with the purchase of materials; a special column is allocated for this, although it is possible that he will purchase it himself and enter this data for clarity. Here's a more thorough look. Pay attention to the last point: the customer even took into account the cost of removing construction waste, which is also important when carrying out major repairs.

Example of an estimate for apartment renovation

This page presents some examples of estimates for construction and repair work.
This examples construction estimates for work already completed (once upon a time, by someone) or abstract estimates on standard roof repair, premises renovation, office renovation etc.

All the estimates presented here have one thing in common: all of them were compiled in the Estimate 2007 program.

The estimates given here will clearly show you what it looks like estimate created in the Estimate 2007 program.
The presented files may also contain others that ours can create: KS-2, KS-3, Invoice, Contract Agreement, etc.

For convenience, the list of estimates is divided into groups and each estimate is provided brief description.
Click on the title to download the estimate.

Select group: All groups Landscaping Roof repair Premises repair

The estimate includes a calculation of the cost of work and materials for the repair of a section of metal roofing. public building(Not a private house). The following work is carried out according to the estimate: complete replacement metal roofing on the roof section with preliminary repair of the sheathing and processing wooden elements fire-retardant composition. The area of ​​the roof section being repaired is 730 m2.

Estimate for major repairs soft roof technical floor. Roof area 1,300 m2. The estimate includes a calculation of implementation next works: dismantling the old roofing carpet with garbage removal, dismantling inactive ventilation pipes, installing a new sand concrete screed, priming and installing a new two-layer roofing carpet made of "Uniflex" on fiberglass.

Very revealing office renovation estimate- 500 lines, 11 sections: general construction and finishing works, ventilation and air conditioning, water supply and sewerage, structured cable systems, access control system and other works.